Water and Wastewater Plans for 2008
- Secure permit from the IEPA for the waterline on Illinois Street West of Oregon under Illinois Route 2.
- Provide wastewater service to the planned Hospice Facility South of Oregon.
- Develop a plan for water-main extensions under the BNSF Railroad, looping in the area South of Oregon along Route 2.
- Provide water and wastewater to the planned Senior Center on South Tenth Street.
- Provide water and wastewater to the tentative plan for the new Sinnissippi Center Facility off Pines Road.
- Complete a plan to extend water and wastewater service North of Oregon along Route 2 when the Illinois Department of Transportation rebuilds Route 2 from Oregon to Byron Illinois. Water mains along Fair Street will also be improved along with this project.
- Develop a plan for water and wastewater extensions along River Road to possible development North of Mix Lane.
- Continue the installation of radio read water meters. This will be a continuing process that could take three years to complete.
- Replace a shut-off valve on Liberty Hill at the reservoir. This will require shutting off a third of Oregon’s service to make the necessary repair.
- The City has hope that requirements will be met with the IEPA and a low interest loan from the IEPA revolving loan fund, and the construction can begin on the planned wastewater upgrade.
- Smoke testing will continue into the residential areas of the City, in an attempt to locate illegal storm water discharges into the sanitary sewer.
- Make the necessary improvements in our wastewater plant to eliminate all combined sewer discharges into the Rock River.
- Complete water and wastewater rate study to establish the actual cost of department operations.
- Agree to terms for the management of the City of Oregon water and wastewater department. Oregon will be making decisions about future operations in November of 2008, which might require a new direction.